Chapter 4
Project Integration Management
Project
Integration Management includes the processes required to ensure that the
various elements of the project are properly coordinated. It involves making tradeoffs
among competing objectives and alternatives to meet or exceed stakeholder needs
and expectations. While all project management processes are integrative
to
some extent, the processes described in this chapter are primarily integrative.
Figure 4-1 provides an overview of the following major processes:
4.1
Project Plan Development—integrating and coordinating all project plans to create
a consistent, coherent document.
4.2
Project Plan Execution—carrying out the project plan by performing the
activities included therein.
4.3
Integrated Change Control—coordinating changes across the entire project.
These
processes interact with each other and with the processes in the other knowledge
areas as well. Each process may involve effort from one or more individuals or
groups of individuals, based on the needs of the project. Each process generally
occurs at least once in every project phase. Although the processes are
presented here as discrete elements with welldefined interfaces, in practice
they may overlap and interact in ways not detailed here. Process interactions
are discussed in detail in Chapter 3. The processes, tools, and techniques used
to integrate project management processes are the focus of this chapter.
For example, project integration management comes into play when a cost
estimate is needed for a contingency plan, or when risks associated with
various staffing alternatives must be identified. However, for a project to be
completed successfully, integration must also occur in a number of other areas
as well. For example:
-The
work of the project must be integrated with the ongoing operations of the performing
organization.
-Product
scope and project scope must be integrated (the difference between product and
project scope is discussed in the introduction to Chapter 5).
One
of the techniques used to both integrate the various processes and to measure the
performance of the project as it moves from initiation through to completion is
Earned Value Management (EVM). EVM will be discussed in this chapter as a
project integrating methodology, while earned value (EV), the technique, will be
discussed in other chapters as a tool to measure performance against the
project plan. Project management software is a tool that aids integration
within a project. And it may span all project management processes.
4.1
PROJECT PLAN DEVELOPMENT
Project
plan development uses the outputs of the other planning processes, including
strategic planning, to create a consistent, coherent document that can be used
to guide both project execution and project control. This process is almost
always iterated several times. For example, the initial draft may include generic
resource requirements and an undated sequence of activities while the subsequent
versions of the plan will include specific resources and explicit dates. The
project scope of work is an iterative process that is generally done by the project
team with the use of a Work Breakdown Structure (WBS), allowing the team to
capture and then decompose all of the work of the project. All of the defined
work must be planned, estimated and scheduled, and authorized with the use of
detailed integrated management control plans sometimes called Control Account
Plans, or CAPs, in the EVM process. The sum of all the integrated management
control plans will constitute the total project scope.
The
project plan is used to:
-Guide
project execution.-Document project planning assumptions.
-Document project planning decisions regarding alternatives chosen.
-Facilitate communication among stakeholders.
-Define key management reviews as to content, extent, and timing.
-Provide a baseline for progress measurement and project control.
4.1.1
Inputs to Project Plan Development
1 Other planning outputs. All of the outputs of the planning processes in the other
knowledge areas (Section 3.3 provides a summary of these project planning processes)
are inputs to developing the project plan. Other planning outputs include both
base documents, such as the WBS, and the supporting detail. Many projects will also
require application area-specific inputs (e.g., most major projects will
require a cash-flow forecast).
2 Historical information. The available historical information (e.g., estimating
databases, records of past project performance) should have been consulted
during the other project planning processes. This information should also be available
during project plan development to assist with verifying assumptions and assessing
alternatives that are identified as part of this process.
3 Organizational policies. Any and all of the organizations involved in the project
may have formal and informal policies whose effects must be considered.
Organizational policies that typically must be considered include, but are not
limited to:
-Quality
management—process audits, continuous improvement targets.
-Personnel
administration—hiring and firing guidelines, employee performance reviews.
-Financial
controls—time reporting, required expenditure and disbursement reviews,
accounting codes, standard contract provisions.
4 Constraints. A
constraint is an applicable restriction that will affect the performance of the
project. For example, a predefined budget is a constraint that is highly likely
to limit the team’s options regarding scope, staffing, and schedule. When a
project is performed under contract, contractual provisions will generally be
constraints.
5 Assumptions. Assumptions
are factors that, for planning purposes, are considered to be true, real, or
certain. Assumptions affect all aspects of project planning, and are part of
the progressive elaboration of the project. Project teams frequently identify,
document, and validate assumptions as part of their planning process. For
example, if the date that a key person will become available is uncertain, the
team may assume a specific start date. Assumptions generally involve a degree
of risk.
4.1.2
Tools and Techniques for Project Plan Development
1 Project planning methodology. A project planning methodology is any structured approach
used to guide the project team during development of the project plan. It may
be as simple as standard forms and templates (whether paper or electronic, formal
or informal) or as complex as a series of required simulations (e.g., Monte
Carlo analysis of schedule risk). Most project planning methodologies make use
of a combination of “hard” tools, such as project management software, and
“soft” tools, such as facilitated startup meetings.
2 Stakeholder skills and knowledge. Every stakeholder has skills and knowledge that may be
useful in developing the project plan. The project management team must create
an environment in which the stakeholders can contribute appropriately (see also
Section 9.3, Team Development). Who contributes, what they contribute, and when
they contribute will vary. For example:
-On a construction project being done under a lump-sum contract, the professional cost engineer will make a major contribution to the profitability objective during proposal preparation when the contract amount is being determined.
-On a construction project being done under a lump-sum contract, the professional cost engineer will make a major contribution to the profitability objective during proposal preparation when the contract amount is being determined.
-On
a project where staffing is defined in advance, the individual contributors may
contribute significantly to meeting cost and schedule objectives by reviewing
duration and effort estimates for reasonableness.
3 Project management information system (PMIS). A PMIS consists of the tools and techniques used to
gather, integrate, and disseminate the outputs of project management processes.
It is used to support all aspects of the project from initiating through
closing, and can include both manual and automated systems.
4 Earned value management (EVM). A technique used to integrate the project’s scope,
schedule, and resources and to measure and report project performance from
initiation to closeout. Further discussions on EVM can be found in Section 7.4.2.3.
4.1.3
Outputs from Project Plan Development
1 Project plan. The
project plan is a formal, approved document used to manage project execution.
The project schedule lists planned dates for performing activities and meeting
milestones identified in the project plan (see Section 6.4.3.1). The project
plan and schedule should be distributed as defined in the communications management
plan (e.g., management of the performing organization may require broad
coverage with little detail, while a contractor may require complete details on
a single subject). In some application areas, the term integrated project
plan is used to refer to this document. A clear distinction should be made
between the project plan and the project performance measurement baselines. The
project plan is a document or collection of documents that should be expected
to change over time as more information becomes available about the project.
The performance measurement baselines will usually change only intermittently,
and then generally only in response to an approved scope of work or deliverable
change. There are many ways to organize and present the project plan, but it
commonly includes all of the following (these items are described in more
detail elsewhere):
-Project
charter.
-A
description of the project management approach or strategy (a summary of the
individual management plans from the other knowledge areas).
-Scope
statement, which includes the project objectives and the project deliverables.
-WBS
to the level at which control will be exercised, as a baseline scope document.
-Cost
estimates, scheduled start and finish dates (schedule), and responsibility assignments
for each deliverable within the WBS to the level at which control will be
exercised.
-Performance
measurement baselines for technical scope, schedule, and cost—i.e., the
schedule baseline (project schedule) and the cost baseline (timephased project
budget).
-Major
milestones and target dates for each.
-Key
or required staff and their expected cost and/or effort.
-Risk
management plan, including: key risks, including constraints and assumptions,
and planned responses and contingencies (where appropriate) for each.
-Subsidiary
management plans, namely:
-Scope
management plan (Section 5.2.3.3).
-Schedule
management plan (Section 6.4.3.3).
-Cost
management plan (Section 7.2.3.3).
-Quality
management plan (Section 8.1.3.1).
-Staffing
management plan (Section 9.1.3.2).
-Communications
management plan (Section 10.1.3.1).
-Risk
response plan (Section 11.5.3.1).
-Procurement
management plan (Section 12.1.3.1).
Each
of these plans could be included if needed and with detail to the extent required
for each specific project.
-Open
issues and pending decisions.
Other
project planning outputs should be included in the formal plan, based upon the
needs of the individual project. For example, the project plan for a large project
will generally include a project organization chart.
2 Supporting detail. Supporting
detail for the project plan includes:
-Outputs
from other planning processes that are not included in the project plan.
-Additional
information or documentation generated during development of the project plan
(e.g., constraints and assumptions that were not previously known).
-Technical
documentation; such as, a history of all requirements, specifications, and
conceptual designs.
-Documentation
of relevant standards.
-Specifications
from early project development planning.
This
material should be organized as needed to facilitate its use during project
plan execution.
4.2
PROJECT PLAN EXECUTION
Project
plan execution is the primary process for carrying out the project plan—the
vast majority of the project’s budget will be expended in performing this process.
In this process, the project manager and the project management team must
coordinate and direct the various technical and organizational interfaces that
exist in the project. It is the project process that is most directly affected
by the project application area in that the product of the project is actually
created here. Performance against the project baseline must be continuously
monitored so that corrective actions can be taken based on actual performance
against the project plan. Periodic forecasts of the final cost and schedule
results will be made to support the analysis.
4.2.1
Inputs to Project Plan Execution
1 Project plan. The
project plan is described in Section 4.1.3.1. The subsidiary management plans
(scope management plan, risk management plan, procurement management plan,
configuration management plan, etc.) and the performance measurement baselines
are key inputs to project plan execution.
2 Supporting detail. Supporting
detail is described in Section 4.1.3.2.
3 Organizational policies. Organizational policies are described in Section 4.1.1.3.
Any and all of the organizations involved in the project may have formal and informal
policies that may affect project plan execution.
4 Preventive action. Preventive
action is anything that reduces the probability of potential consequences of
project risk events.
5 Corrective action. Corrective
action is anything done to bring expected future project performance in line
with the project plan. Corrective action is an output of the various control
processes—as an input here it completes the feedback loop needed to ensure
effective project management.
4.2.2
Tools and Techniques for Project Plan Execution
1 General management skills. General management skills such as leadership,
communicating, and negotiating are essential to effective project plan
execution. General management skills are described in Section 2.4.
2 Product skills and knowledge. The project team must have access to an appropriate set
of skills and knowledge about the project’s product. The necessary skills are
defined as part of planning (especially in resource planning, Section 7.1) and are
provided through the staff acquisition process (described in Section 9.2).
3 Work authorization system. A work authorization system is a formal procedure for sanctioning
project work to ensure that work is done at the right time and in the proper
sequence. The primary mechanism is typically a written authorization to begin
work on a specific activity or work package. The design of a work authorization
system should balance the value of the control provided with the cost of that
control. For example, on many smaller projects, verbal authorizations will be
adequate.
4 Status review meetings. Status review meetings are regularly scheduled meetings held
to exchange information about the project. On most projects, status review
meetings will be held at various frequencies and on different levels (e.g.,the
project management team may meet weekly by itself and monthly with the customer).
5 Project management information system. The PMIS is described in Section 4.1.2.3.
6 Organizational procedures. Any and all of the organizations involved in the project may
have formal and informal procedures that are useful during project execution.
4.2.3
Outputs from Project Plan Execution
1 Work results. Work
results are the outcomes of the activities performed to accomplish the project.
Information on work results—which deliverables have been completed and which
have not, to what extent quality standards are being met, what costs have been
incurred or committed, etc.—is collected as part of project plan execution and
fed into the performance reporting process (see Section 10.3 for a more
detailed discussion of performance reporting). It should be noted that although
outcomes are frequently tangible deliverables such as buildings, roads, etc.,
they are also often intangibles such as people trained who can effectively apply
that training.
2 Change requests. Change
requests (e.g., to expand or contract project scope, to modify cost [budgets],
or schedule estimates [dates, etc.]) are often identified while the work of the
project is being done.
4.3
INTEGRATED CHANGE CONTROL
Integrated
change control is concerned with a) influencing the factors that create changes
to ensure that changes are agreed upon , b) determining that a change has
occurred, and c) managing the actual changes when and as they occur. The original
defined project scope and the integrated performance baseline must be maintained
by continuously managing changes to the baseline, either by rejecting new
changes or by approving changes and incorporating them into a revised project
baseline. Integrated change control requires:
-Maintaining
the integrity of the performance measurement baselines.
-Ensuring
that changes to the product scope are reflected in the definition of the
project scope. (The difference between product and project scope is discussed in
the introduction to Chapter 5.)
-Coordinating
changes across knowledge areas, as illustrated in Figure 4-2. For example,
a proposed schedule change will often affect cost, risk, quality, and staffing.
4.3.1
Inputs to Integrated Change Control
1 Project plan. The
project plan provides the baseline against which changes will be controlled
(see Section 4.1.3.1).
2 Performance reports. Performance
reports (described in Section 10.3) provide information on project performance.
Performance reports may also alert the project team to issues that may cause
problems in the future.
3 Change requests. Change
requests may occur in many forms—oral or written, direct or indirect,
externally or internally initiated, and legally mandated or optional.
4.3.2
Tools and Techniques for Integrated Change Control
1 Change control system. A change control system is a collection of formal,
documented procedures that defines how project performance will be monitored
and evaluated, and includes the steps by which official project documents may
be changed. It includes the paperwork, tracking systems, processes, and
approval levels necessary for authorizing changes. In many cases, the
performing organization will have a change control system that can be adopted
“as is” for use by the project. However, if an appropriate system is not
available, the project management team will need to develop one as part of the
project. Many change control systems include a group responsible for approving
or rejecting proposed changes. The roles and responsibilities of these groups
are clearly defined within the change control system and agreed upon by all key
stakeholders. Organizations vary by the definition of the board; however, some common
occurrences are Configuration Control Board (CCB), Engineering Review Board
(ERB), Technical Review Board (TRB), Technical Assessment Board (TAB), and a
variety of others. The change control system must also include procedures to
handle changes that may be approved without prior review, for example, as the
result of emergencies. Typically, a change control system will allow for “automatic”
approval of defined categories of changes. These changes must still be
documented and captured so that the evolution of the baseline can be
documented.
2 Configuration management. Configuration management is any documented procedure used
to apply technical and administrative direction and surveillance to:
-Identify
and document the functional and physical characteristics of an item or system.
-Control
any changes to such characteristics.
-Record
and report the change and its implementation status.
-Audit
the items and system to verify conformance to requirements.
In
many application areas, configuration management is a subset of the change control
system and is used to ensure that the description of the project’s product is
correct and complete. In other application areas, change control refers to any systematic
effort to manage project change.
3 Performance measurement. Performance measurement techniques such as EV (described
in Section 10.3.2.4) help to assess whether variances from the plan require
corrective action.
4 Additional planning. Projects
seldom run exactly according to plan. Prospective changes may require new or
revised cost estimates, modified activity sequences, schedules, resource
requirements, analysis of risk response alternatives, or other adjustments to
the project plan.
5 Project management information system. PMIS is described in Section 4.1.2.3.
4.3.3
Outputs from Integrated Change Control
1 Project plan updates. Project plan updates are any modification to the contents
of the project plan or the supporting detail (described in Sections 4.1.3.1 and
4.1.3.2, respectively). Appropriate stakeholders must be notified as needed.
2 Corrective action. Corrective
action is described in Section 4.2.1.5.
3 Lessons learned. The
causes of variances, the reasoning behind the corrective action chosen, and
other types of lessons learned should be documented so that they become part of
the historical database for both this project and other projects of the performing
organization. The database is also the basis for knowledge management.
SUMBER : Project Management Institute, “A Guide To The Project Management Body Of
Knowledge”, Newton Square, USA, 1996.
0 komentar:
Posting Komentar